Actuator Housing

ProductionA356ComplexHealthyactuator-housing

Where this job stands

Thin boss wall at the encoder end drove the first two trials. Wall grew to 3.2mm at R4 and the shrink porosity cleared.

Commercial

Tooling cost
$6,252
Committed volume
1,200 pcs
Quote
Q-2601-RIDGE-01Geometry
Quoted per piece
$15.89
Break-even against CNC
71 pcs
Rework buffer
Included in quote

Geometry

Solid volume
218,400 mm3
Intersection volume
262,080 mm3
Bounding box
148 x 96 x 62 mm
Casting weight
0.702 kg
Parts per mold
8recomputed 8
STEP file
uploads/ridgeline/actuator-housing-r4.step

Casting trials

3
TrialDateOutcomeGoalPourMold
T1Feb 4FailureFirst pour off the printed sand tool. Confirm the gating fills the encoder boss.705C180C
T2Feb 18PartialAdd a second riser over the top rib and raise pour temp.725C185C
T3gradMar 5SuccessProve the 3.2mm boss wall from the R4 model.722C185C

Production runs

3
97.2% yield
DateOrderedDeliveredYield$/pcMarginBatch
Mar 1930028896.0%$18.7531.2%A356-2603-E
May 740039298.0%$17.4834.8%A356-2605-B
Jul 250048697.2%$17.0036.1%A356-2607-A

Rework

2
8.5 hrs
LoggedTriggerStatusWhat happenedHrs
May 9DimensionalResolved
Eight parts out of tolerance on the bolt circle after the tool was re-seated.
Fix: Re-machined the bolt circle. Added a tool seating check to the run sheet.
Run of May 7
3.0
Mar 21PorosityResolved
Twelve parts from the first run showed porosity at the encoder boss on x-ray.
Fix: Scrapped. Riser height raised 8mm for the remainder of the run.
Run of Mar 19
5.5

Porosity observations

3
LoggedWhereSeverityCauseFixResolved
Jul 4Top rib, traceMinorTemperatureMold temp held tighter with a preheat cycle.Yes
May 8Encoder boss, trace onlyMinorDesignAccepted. Below the customer x-ray threshold.Yes
Mar 20Encoder boss, 6mm below the top faceSevereDesignBoss wall thickened to 3.2mm in R4.Yes

Post-mortem

completed Jul 24, 2026
Tooling actual
$6,971
Tooling delta
+$719
Per piece actual
$17.74
Per piece delta
+$1.85
Rework cost
$1,275
Labour
226.5 hrs
What went wrong

Two trials were spent adding feeding to a section that was simply too thin. The wall fix was available from the first x-ray.

What to do differently

When porosity sits in a boss, check the wall against the section rule before touching the gating.

Notes

Three runs in and per piece cost is still falling as the crew learns the tool.

Knowledge from this job

2
Job opened Jan 20, 2026 · 3 trials · 3 runs · 1,166 pieces delivered