Turbine Inlet Housing

On holdA356ComplexAt riskturbine-inlet-housing

Where this job stands

Held pending a customer redesign. Two trials in and both failed on cold shut across the top flange.

Commercial

Tooling cost
$5,811
Committed volume
300 pcs
Quote
Q-2603-KEST-01Geometry
Quoted per piece
$40.18
Break-even against CNC
17 pcs
Rework buffer
Included in quote

Geometry

Solid volume
412,600 mm3
Intersection volume
561,100 mm3
Bounding box
164 x 164 x 96 mm
Casting weight
1.504 kg
Parts per mold
1recomputed 1
STEP file
uploads/kestrel/inlet-housing-r2.step

Casting trials

2
TrialDateOutcomeGoalPourMold
T1Mar 30FailureFirst pour of the largest part on the floor.730C200C
T2Apr 27FailureRaise pour temp and add a second gate to close the flange.745C210C

Production runs

0
DateOrderedDeliveredYield$/pcMarginBatch
No production runs

Rework

1
LoggedTriggerStatusWhat happenedHrs
May 4OtherUnresolved
Trial 2 flange cold shut. Job held while the customer redesigns the flange.
0.0

Porosity observations

0
LoggedWhereSeverityCauseFixResolved
Nothing observed

Knowledge from this job

0

Nothing captured against this job yet.

Job opened Mar 9, 2026 · 2 trials · 0 runs · 0 pieces delivered