Pump Volute·Vantage Thermal

Trial 4

SuccessA413Jun 2, 2026graduated to production

Goal

Enlarge the outer wall gate to cut velocity.

Process

Pour temp
690C
Mold temp
195C
Alloy batch
A413-2606-A
Trial date
Jun 2, 2026
Gating
Outer wall gate, doubled area.
Changed from the previous trial
Gate area doubled.

What came out

Defects observed

Clean on section at both the throat and the outer wall across six parts.

Lessons learned

Two jobs in a row fixed by opening the gate. Default to a bigger gate and only shrink it if flash appears.

Trial sequence

4